I&C TEAMS
Chrysler Corporation Missile Division’s Michigan Ordnance Plant (MOP), located at Sterling Heights, Warren, Michigan, began
supplying Jupiter missiles to the USAF by 28 August 1958. Chrysler, the prime contractor for fabricating the Jupiter missiles, was
also contracted to install and verify each missile’s operational status at their intended locations in Europe. These capabilities were
created with the formation of two Installation and Checkout (I&C) Teams that would engage in the installation and verification of
these missile’s capabilities under the USAFTA banner in Europe, pending siting agreements with Italy (NATO I) and Turkey (NATO II).
These two teams, I&C Team I and I&C Team II, would be sent first to Italy (NATO I) to complete the installation and checkout of the
two missile squadrons there, each consisting of five launch positions of three missiles each. Upon completion of all 10 launch
positions in Italy the two teams would then be dispatched to Turkey to complete the installation and checkout of the last missile
squadron consisting of five launch positions of three missiles each.
By August of 1959 siting agreements with Italy (NATO I) had been completed with an operational readiness date of 1 May 1960
being established. The first launch position in Italy was actually completed by the I&C Teams on 11 July 1960, the last (10th)
position was completed on 20 June 1961. After Chrysler Corporation Missile Division’s I&C Teams completed their NATO I Jupiter
installations and checkout in Italy they headed for Turkey to complete the 2nd phase of Jupiter installations under the established
NATO II deployment plans.
Initial Government-to-Government (GTG) Jupiter siting agreements had been reached with Turkey (NATO II) on 28 October 1959.
Several remaining issues were settled by 1 June 1960. Chrysler Corporation Missile Division (USAFTA) I&C Teams were operating
out of the RIM located at Çigli AFB near Izmir, Turkey by August of 1961. The first launch position, LP-1, in Turkey was scheduled for
completion by 1 June 1961, with the last position, LP-5, having been completed in February of 1962.
By February of 1962 the last of the five Turkish sites, LP-5, was completed by I&C Team II and the contract came to an end. The I&C
Teams dissolved. The Team’s English contractors headed back to England, their Turkish laborers melted back into the countryside,
and the Chrysler Corporation I&C employees headed back to Michigan anticipating work with Chrysler’s new Saturn Project.
I&C TEAMS
Chrysler Corporation Missile Division’s Michigan Ordnance Plant
(MOP), located at Sterling Heights, Warren, Michigan, began
supplying Jupiter missiles to the USAF by 28 August 1958. Chrysler,
the prime contractor for fabricating the Jupiter missiles, was also
contracted to install and verify each missile’s operational status at
their intended locations in Europe. These capabilities were created
with the formation of two Installation and Checkout (I&C) Teams
that would engage in the installation and verification of these
missile’s capabilities under the USAFTA banner in Europe, pending
siting agreements with Italy (NATO I) and Turkey (NATO II).
These two teams, I&C Team I and I&C Team II, would be sent first to
Italy (NATO I) to complete the installation and checkout of the two
missile squadrons there, each consisting of five launch positions of
three missiles each. Upon completion of all 10 launch positions in
Italy the two teams would then be dispatched to Turkey to
complete the installation and checkout of the last missile squadron
consisting of five launch positions of three missiles each.
By August of 1959 siting agreements with Italy (NATO I) had been
completed with an operational readiness date of 1 May 1960 being
established. The first launch position in Italy was actually
completed by the I&C Teams on 11 July 1960, the last (10th)
position was completed on 20 June 1961. After Chrysler
Corporation Missile Division’s I&C Teams completed their NATO I
Jupiter installations and checkout in Italy they headed for Turkey to
complete the 2nd phase of Jupiter installations under the
established NATO II deployment plans.
Initial Government-to-Government (GTG) Jupiter siting agreements
had been reached with Turkey (NATO II) on 28 October 1959.
Several remaining issues were settled by 1 June 1960. Chrysler
Corporation Missile Division (USAFTA) I&C Teams were operating
out of the RIM located at Çigli AFB near Izmir, Turkey by August of
1961. The first launch position, LP-1, in Turkey was scheduled for
completion by 1 June 1961, with the last position, LP-5, having been
completed in February of 1962.
By February of 1962 the last of the five Turkish sites, LP-5, was
completed by I&C Team II and the contract came to an end. The I&C
Teams dissolved. The Team’s English contractors headed back to
England, their Turkish laborers melted back into the countryside,
and the Chrysler Corporation I&C employees headed back to
Michigan anticipating work with Chrysler’s new Saturn Project.