HISTORY - Page 37
By August, decision time was nearing, so the Secretary
of Defense set up art ad hoc committee, comprised of
Mr. W. M. Holaday from his office, General Medaris,
and General Schriever, to work out a single land-based
IRBM program. All aspects of both systems were to be
studied, with particular attention being given to basic
missile design, over-all program status, and
manufacturing and test facilities contributing to the
development program. After careful deliberation, the
committee was to make a recommendation to the
Secretary by 15 September.
While this study was in progress, explicit guidelines
were given for program operations in being. ABMA was
told not to commit funds for missiles or missile
components beyond those needed to meet a
production rate of one missile per month. In turn, lead
time commitments for procurement would be limited
to 12 months. Anything beyond that time frame,
whether it was procurement of development activity,
should be suspended or canceled. ABMA and
contractor personnel were also limited to an overtime
rate of three per cent, with the exception of personnel
directly connected with static and flight testing
47
.
To ABMA's thinking, the Secretary's decision had an
adverse impact upon the effectiveness of the Agency's
operations. For example, Genera Medaris felt that the
three per cent limitation reduced his work force at a
rate equal to 1,000 people. This meant that the Agency
would be operating at a relative strength of 65 per
cent, which, in turn, threatened a number of
programs. For example, it was likely that ABMA
participation in the Atomic Energy Commission's (AEC)
Project HARDTACK would be canceled if the Agency
were unable
_____________________________
47. Memo, S/D to S/A, 13 Aug 57, subj: IRBM Pro, Hist Off files.